Saturday, March 30, 2013

Foundation Work


Interior wall footer  4/6/2013




West exterior wall footer  4/6/2013

























Pouring Elevator Pit Pad  3/28/2013 











 
 Elevator Pit 3/29/2013





Tuesday, March 26, 2013

Utilities to the Site

Installing sanitary line  3/20/2013




















Tapping into 12" main water line  3/21/2013


























6" on left for Fire water
   4" on right for Domestic water  3/21/2013




Drilling hole into storm water line   3/26/2013



















Ready for storm water line   3/26/2013

























Storm Water Tap Complete   3/26/2013



























Tuesday, March 12, 2013

Eric Snow YMCA Construction Site Preparation

Equipment to prepare site for construction   3/12/2013


Surveying Site   3/12/2013






Bringing site to grade before construction begins   3/12/2013

Site is almost to grade  3/18/2013